1. Home
  2. Glossary
  3. Back-timing

Glossary

Back-timing

Updated
DEFINITION

Back-timing is working out when each segment must start by counting backward from a fixed end time. A row's back time is the latest it can start if everything after it runs to plan and the show still ends on time.

Worked example

A 30-minute news programme off air at 18:30:00. Start from the bottom and subtract each duration.

Item Duration Back time (latest start)
Headlines 1:00 18:00:00
Lead package 2:30 18:01:00
Studio interview 6:00 18:03:30
Break 3:00 18:09:30
... ... ...
Weather 2:30 18:26:30
Goodbye 1:00 18:29:00
Off air 18:30:00

If the interview actually starts at 18:04:30, the show is a minute heavy, and a minute has to come out of something still to come. Newsroom systems such as ENPS show this as a backtime column calculated from the show's end (Syracuse University ENPS guide).

Back time and front time

Front timing counts forward from the start to show when each row will begin as planned. Back timing counts back from the end to show when each row must begin (Cuez help centre). When the two agree, the show is on time; the gap between them is how far over or under you are.

The back-timing guide covers how to recover time once you know you are over.

All 56 terms in the glossary

See it run before your next show.

Open the sample room, start a cue, add a minute and send a message. No account needed.

Try a sample room