Back-timing and hard outs
Shows are easy to start on time and hard to end on time. Back-timing is the arithmetic that tells you, at any moment, whether you will make it.
Back-timing is working backward from a fixed end time, the hard out, to find the latest moment each segment can start. Subtract each remaining duration from the hard out, last segment first. During the show, compare those times with the clock. If you are later than the back-timed start, you are over and something has to shrink.
ON THIS PAGE
The terms
- Hard out: a time the show must end, with a consequence if it does not. The broadcast cuts away, the venue charges overtime, the room turns over to another event.
- Soft out: a planned end that can slide a little. "About five" is a soft out.
- Hard start (or hard time): a segment that must begin at an exact clock time, such as a live cross to another city or a countdown to midnight.
- Back-timing: calculating start times backward from a fixed end, instead of forward from the start.
- Over and under: how far the show is behind or ahead of the plan right now. Plus four minutes means four minutes late.
How to back-time a run of show
Front-timing answers "if we start at 9:00, when do we finish?" Back-timing answers "if we must finish at 12:30, when is the latest each thing can start?"
- Write the hard out at the bottom.
- Subtract the last segment's duration. That is its latest start.
- Subtract the one before it, and so on to the top.
- Compare the first back-timed start with your planned show start. The difference is your slack. If it is negative, the show does not fit.
Worked example
Hard out at 12:30. Five segments remain.
| Segment | Duration | Front-timed start | Back-timed latest start | Slack |
|---|---|---|---|---|
| Panel | 30:00 | 11:00 | 11:05 | 5:00 |
| Transition | 02:00 | 11:30 | 11:35 | 5:00 |
| Closing keynote | 35:00 | 11:32 | 11:37 | 5:00 |
| Awards | 12:00 | 12:07 | 12:12 | 5:00 |
| Close and thanks | 06:00 | 12:19 | 12:24 | 5:00 |
| Show ends | 12:25 | 12:30 |
The plan finishes at 12:25, five minutes before the hard out. That five minutes is the only cushion in the last ninety minutes of the day. If the panel starts at 11:06, the cushion has gone and the show is one minute over, even though nothing has visibly gone wrong yet.
The back-time calculator does this for any list of segments.
Reading over and under during the show
Over/under is one number that summarizes the whole day:
over/under = (now + time left in the current item + all remaining durations) − planned end
- Under (negative) means you are ahead. You can let a good Q&A run.
- Zero means on plan.
- Over (positive) means that without a change you will finish late by that much.
It matters more than whether the current speaker is over, because it accounts for time already gained or lost. A speaker who runs three minutes long in a show that is four minutes under has cost you nothing.
runofsho calculates over/under for you and updates it every time an item starts, ends or changes length.
Where to recover time
Decide the order before the show. From least to most painful:
| Lever | Typical saving | Cost |
|---|---|---|
| Tighten transitions and walk-ons | 0:30 to 1:00 each | None the audience notices |
| Shorten housekeeping and reads | 1:00 to 2:00 | None |
| Trim Q&A | 3:00 to 10:00 | Fewer questions |
| Shorten a break | 5:00 | Longer queues, slower return |
| Drop a video or sting | 1:00 to 3:00 | Client may mind |
| Ask a speaker to shorten | Varies | Needs warning before they walk on |
| Cut a segment | All of it | Producer and client decision |
Two rules of thumb. Recover early: three minutes found before lunch is easier than three minutes found in the closing keynote. And recover in small pieces: five cuts of one minute are invisible, one cut of five is not.
Padding: where to hide it
Slack inside a talk gets used by the speaker. Slack that looks like something else can be taken back.
- Give breaks five more minutes than you need.
- Schedule Q&A as its own row so it can shrink.
- End the plan a few minutes before the hard out, as in the example above.
- Do not publish the padded times to the audience. The agenda says 10:30. The run of show says 10:27.
Hard starts in the middle of a show
Some segments must begin at a fixed clock time regardless of what came before: a satellite window, a remote guest, a moment tied to the hour. Treat each one as a small hard out for everything before it. Back-time the preceding segments to that point, and plan a filler you can stretch or drop (a host chat, a video, music) directly before it.
When you cannot make the hard out
Say so early and plainly: "At this pace we finish at 12:36. To make 12:30 I need six minutes. I suggest Q&A to five and drop the sponsor video." The producer decides. The show caller's job is to bring the number and the options while there is still time to use them. More on that in how to call a show.
FAQ
What is back-timing?
Calculating when each segment must start by working backward from a fixed end time. It is used in broadcast and live events to make sure a show ends exactly when it has to.
What is a hard out?
A fixed end time with real consequences if it is missed, such as a broadcast window closing or a venue's overtime charge. A soft out is a planned end that can move.
What does over/under mean on a rundown?
It is how many minutes and seconds the show is running behind (over) or ahead (under) of the plan, taking into account everything still to come.
How do I back-time in a spreadsheet?
Put the hard out in the last row. In each row above, subtract that row's duration from the start time of the row below. The top value is the latest you can start.
How much padding should a show have?
Enough to absorb one thing going wrong. Many producers aim to finish the plan a few minutes before the hard out and keep extra slack in breaks and Q&A rather than in talks.