How to build a run of show
A working method for going from a blank sheet to a document a crew can run a show from.
Start from the two times that cannot move: when the show starts and when it must end. List every segment in order, give each one a duration, and let start times calculate. Add who is on stage and one column per crew department, number the cues, mark what can be cut, then walk it through with the crew before show day.
ON THIS PAGE
- Step 1: Fix the two times that cannot move
- Step 2: List every segment, including the ones nobody mentions
- Step 3: Give every row a duration, not a start time
- Step 4: Check the total against the hard out
- Step 5: Add who is on stage and what the audience sees
- Step 6: Add one column per department
- Step 7: Number the cues
- Step 8: Mark where time can be recovered
- Step 9: Walk it through, lock it, then record what really happened
- A worked example
- FAQ
If you have never seen one, start with what a run of show is. If you would rather edit than start from zero, open a template in the free builder and follow along.
Step 1: Fix the two times that cannot move
Write down the show start and the hard out before anything else. The start is usually set by the invitation. The hard out is set by something outside your control: the venue contract, a broadcast window, a flight, the next event in the room. Everything else is negotiable. These two are not.
Subtract one from the other. That is your running time. A 9:00 start with a 12:30 hard out is 210 minutes, and no amount of optimism makes it 220.
Step 2: List every segment, including the ones nobody mentions
Write one row for each thing that happens, in order. Start with the content the client gave you, then add what they left out:
- Doors and walk-in
- Opening video or music sting
- Introductions between speakers
- Walk-ons, walk-offs and lectern resets
- Q&A after talks
- Sponsor reads and housekeeping announcements
- Breaks, and the time it takes to get people back
- The close, thank-yous and walk-out music
A useful test: if a department has to press something, it is a row.
Step 3: Give every row a duration, not a start time
Enter how long each segment lasts. Let the start times calculate from the top down. This is the single most important habit in the whole process, because durations are what change. When a speaker asks for five more minutes, you change one cell and every start time after it follows.
Be honest about lengths. Ask speakers for their script or slide count. A talk at a comfortable presentation pace runs at roughly 130 words a minute, so a 2,600-word script is a 20-minute talk. The speech length calculator does that sum.
Step 4: Check the total against the hard out
Add up the durations. If the total is longer than your running time, you have a problem to solve now rather than on stage. Options, in the order producers usually prefer them:
- Shorten transitions and housekeeping.
- Shorten or merge Q&A.
- Shorten breaks, but not below ten minutes for a large room.
- Ask speakers to trim.
- Cut a segment.
The back-time calculator works backward from the hard out and shows the latest time each segment can start.
Step 5: Add who is on stage and what the audience sees
For each row, name the person and describe the segment the way the audience will experience it. "Panel: Building for Scale" with four names tells the stage manager how many chairs and microphones to set. "Panel" does not.
Step 6: Add one column per department
Give audio, lighting, video or graphics, and camera their own columns, and write one short instruction per row: the microphone, the lighting look, the slide deck or video file, the shot. Keep it to what changes. If lighting holds the same look for forty minutes, the cell is empty after the first row.
Ask each department head to fill in or correct their own column. They know their cues better than you do, and they will trust a document they helped write.
Step 7: Number the cues
Number every row. On show day the caller says "standby cue 14" and five people look at the same line. If you insert a row late, use 14A rather than renumbering everything the crew has already memorized.
Step 8: Mark where time can be recovered
Decide in advance what gets shortened if the show runs long, and write it in the notes: "Q&A can drop to 5:00", "skip VT3 if over by more than 3:00". Build a little slack into breaks and Q&A rather than into talks. Slack inside a talk gets used by the speaker. Slack in a break can be taken back.
Step 9: Walk it through, lock it, then record what really happened
Read the run of show aloud with the crew, top to bottom, before show day. This is a paper tech, and it finds missing rows faster than any other method. Then freeze a version so everyone knows which one is live, and make changes in one place only.
During the show, note the actual start and length of each segment. Afterward, the difference between planned and actual is the most useful thing you will take into the next event with the same client.
A worked example
Here is the opening of a half-day conference after steps 1 to 7. Running time available: 210 minutes.
| Cue | Start | Duration | Segment | Who | Audio | Graphics |
|---|---|---|---|---|---|---|
| 1 | 08:30 | 30:00 | Doors and walk-in | Walk-in playlist | Holding slide | |
| 2 | 09:00 | 01:30 | Opening video | VT audio | Roll VT1 | |
| 3 | 09:01 | 03:30 | Welcome and housekeeping | Host | HH1 | Host lower third |
| 4 | 09:05 | 20:00 | Keynote | CEO | Lav 2 | Keynote deck |
| 5 | 09:25 | 10:00 | Q&A (can drop to 5:00) | CEO, Host | HH1, HH3 | Q&A slide |
| 6 | 09:35 | 01:00 | Transition | Sting | Session title |
FAQ
How far in advance should a run of show be finished?
Have a complete first version a week before a conference so departments can add their cues, and a locked version the day before. Expect changes until doors.
Should I use start times or durations?
Durations. Start times are the result of durations, not an input. The only start times you set by hand are the show start and any segment that must begin at a fixed clock time, such as a satellite link.
How much buffer should I add?
There is no universal figure. A common approach is to keep talks at their agreed length and hold the slack in Q&A and breaks, where it can be recovered without cutting anyone off.
What software do I need?
A spreadsheet is enough to plan with. To run the show live, with a highlighted current cue, automatic recalculation and timers on stage, use run of show software. See the comparison of the main options.