# Over/under

> Over/under is how far a show is running behind (over) or ahead (under) of plan, counting everything still to come. A worked six-row example and how to recover.

- Canonical: https://runofsho.com/glossary/over-under/
- Last updated: 2026-11-26
- Part of: https://runofsho.com/glossary/

**Definition:** Over/under is how far a show is running behind (over) or ahead (under) of its plan, taking into account everything still to come. It is the projected end time minus the planned end time, so it tells the show caller whether the show will finish on time if nothing changes.

## How it is worked out

> over/under = (now + time left in the current row + every remaining planned duration) − planned end

A positive figure means the show is over, and will finish that much late without a change. A negative figure means it is under, with time in hand. Zero means on plan. Newsrooms say the same thing as "heavy" and "light"; [how to read a TV running order](https://runofsho.com/blog/tv-running-order/) covers that wording.

The figure looks at the whole show, not at the person on stage. A speaker who is two minutes over in a show that is four minutes under has cost nothing.

## Worked example

A conference morning starts at 09:00. The six rows are planned to end at 10:23, and the room has a [hard out](https://runofsho.com/glossary/hard-out/) at 10:25 for the lunch turnover. That leaves two minutes of cushion. The over/under column is the reading after each row ends.

| Row | Planned | Actual | This row | Over/under after it | Projected end |
|---|---|---|---|---|---|
| Welcome and housekeeping | 5:00 | 6:30 | +1:30 | +1:30 | 10:24:30 |
| Opening keynote | 25:00 | 29:00 | +4:00 | +5:30 | 10:28:30 |
| Sponsor video | 3:00 | 3:00 | 0:00 | +5:30 | 10:28:30 |
| Panel with Q&A | 30:00 | 26:00 | −4:00 | +1:30 | 10:24:30 |
| Lightning talks | 15:00 | 14:00 | −1:00 | +0:30 | 10:23:30 |
| Closing remarks | 5:00 | 3:30 | −1:30 | −1:00 | 10:22:00 |

Three moments in that morning:

- **09:20, keynote under way.** The keynote started at 09:06:30 with 25 minutes planned, so 11:30 is left. 09:20 + 11:30 + 53:00 still to come gives 10:24:30, which is +1:30. The speaker is on pace, so the figure does not move while they talk.
- **09:31:30, keynote at zero.** The keynote's countdown runs out, and from here every second it runs is a second added to the over/under. It finishes four minutes long, and the show is +5:30. The projected end of 10:28:30 is now 3:30 past the hard out.
- **After the sponsor video.** The caller tells the producer the show is five and a half over. They agree to cut the panel's Q&A by four minutes, and the moderator gets a wrap cue. The two speakers after that run a little short. The room finishes at 10:22, a minute under and three minutes clear of the hard out.

A sponsor video with a fixed length can't give time back, and a keynote is hard to stop mid-sentence. The recovery came from the [soft](https://runofsho.com/glossary/soft-out/) parts of the show: the Q&A and the walk-ons. The [back-timing guide](https://runofsho.com/guides/back-timing-and-hard-outs/) lists the usual levers, from cheapest to most painful.

## Over/under and time to the hard out

They are separate numbers. Over/under compares the show with its own plan. Time to the hard out compares it with the clock that cannot move. In the example, +1:30 after the welcome still fitted, because the plan had two minutes of cushion. +5:30 did not. A plan with no cushion turns every second over into a second past the hard out.

## Over/under in runofsho

In runofsho the planned end and the over/under update as you edit the rundown and as the show runs. The show caller's presses on the controller record how long each row really ran, so the figure reflects what happened rather than what was planned. It can only be as accurate as those presses: if nobody moves the show on when a row ends, the figure keeps assuming that row is still running. It tells you how far off plan the show is, not what to cut. That decision stays with the producer and the caller.

## Related terms

- [Back-timing](https://runofsho.com/glossary/back-timing/): Calculating when each segment must start by working backward from a fixed end time.
- [Front timing](https://runofsho.com/glossary/front-timing/): Working out when each segment will start by adding durations forward from the show's start time. The front time of a row is its planned start.
- [Float](https://runofsho.com/glossary/float/): To take an item out of the timed running order without deleting it, so the show stops counting it but it can come back if time allows.
- [Hard out](https://runofsho.com/glossary/hard-out/): A fixed end time with consequences if it is missed, such as a broadcast window closing or venue overtime. A soft out can slide.
- [Soft out](https://runofsho.com/glossary/soft-out/): A planned end time that can move without serious consequences, such as the close of a conference session before a coffee break. Compare a hard out, which cannot move.
- [Pad](https://runofsho.com/glossary/#pad): Flexible content or time that can be stretched or cut to make a show hit its end time. A host chat or a Q&A is often the pad.