**Definition:** Front timing works out when each segment will start by adding the durations forward from the show's start time. A row's front time is its planned start if everything before it runs to length.

## Example

An event that opens at 19:00. Each start is the one above it plus the duration above it.

| Start (front time) | Duration | Segment |
|---|---|---|
| 19:00 | 0:05 | Walk-in music ends, voice of God |
| 19:05 | 0:08 | Host welcome |
| 19:13 | 0:20 | Keynote |
| 19:33 | 0:03 | Video |
| 19:36 | 0:25 | Panel |
| 20:01 | | Planned end |

This is what most event run of shows show by default. If the keynote runs 4 minutes long, every front time below it moves 4 minutes later, and the planned end becomes 20:05.

## When to use which

- Front times answer "when will the panel start?" They are what you give presenters, green room staff and caterers.
- [Back times](https://runofsho.com/glossary/back-timing/) answer "when must the panel start to finish on time?" They matter when the end is a [hard out](https://runofsho.com/glossary/hard-out/).

Broadcast rundown tools usually show both; [Rundown Creator's timing guide](https://www.rundowncreator.com/how-it-works/timing-101/) describes front time as the on-air time plus the estimated durations of the items before it.

## Related terms

- [Back-timing](https://runofsho.com/glossary/back-timing/): Calculating when each segment must start by working backward from a fixed end time.
- [Hard start](https://runofsho.com/glossary/#hard-start): A segment that must begin at an exact clock time regardless of what came before, such as a live cross or a stream going on air.
- [Over/under](https://runofsho.com/glossary/#over-under): How far a show is running behind (over) or ahead (under) of the plan, taking into account everything still to come. One of the five numbers a show caller watches.
- [Run of show](https://runofsho.com/glossary/run-of-show/): The minute-by-minute plan for a live event: every segment in order with its start time, duration, people and department notes.