# Back-timing

> Back-timing works out when each segment must start by counting back from a fixed end time. A short definition, a worked rundown and how it differs from front timing.

- Canonical: https://runofsho.com/glossary/back-timing/
- Last updated: 2026-11-24
- Part of: https://runofsho.com/glossary/
- Also called: backtiming, back-time

**Definition:** Back-timing is working out when each segment must start by counting backward from a fixed end time. A row's back time is the latest it can start if everything after it runs to plan and the show still ends on time.

## Worked example

A 30-minute news programme off air at 18:30:00. Start from the bottom and subtract each duration.

| Item | Duration | Back time (latest start) |
|---|---|---|
| Headlines | 1:00 | 18:00:00 |
| Lead package | 2:30 | 18:01:00 |
| Studio interview | 6:00 | 18:03:30 |
| Break | 3:00 | 18:09:30 |
| ... | ... | ... |
| Weather | 2:30 | 18:26:30 |
| Goodbye | 1:00 | 18:29:00 |
| Off air | | 18:30:00 |

If the interview actually starts at 18:04:30, the show is a minute heavy, and a minute has to come out of something still to come. Newsroom systems such as ENPS show this as a backtime column calculated from the show's end ([Syracuse University ENPS guide](https://nccnewslinks.syr.edu/wp-content/uploads/2022/02/ENPS-8-Guide-BDJ-2022.pdf)).

## Back time and front time

[Front timing](https://runofsho.com/glossary/front-timing/) counts forward from the start to show when each row will begin as planned. Back timing counts back from the end to show when each row must begin ([Cuez help centre](https://intercom.help/cuez/en/articles/6847625-how-to-use-the-different-timings-available)). When the two agree, the show is on time; the gap between them is how far over or under you are.

The [back-timing guide](https://runofsho.com/guides/back-timing-and-hard-outs/) covers how to recover time once you know you are over.

## Related terms

- [Front timing](https://runofsho.com/glossary/front-timing/): Working out when each segment will start by adding durations forward from the show's start time. The front time of a row is its planned start.
- [Hard out](https://runofsho.com/glossary/hard-out/): A fixed end time with consequences if it is missed, such as a broadcast window closing or venue overtime. A soft out can slide.
- [Over/under](https://runofsho.com/glossary/#over-under): How far a show is running behind (over) or ahead (under) of the plan, taking into account everything still to come. One of the five numbers a show caller watches.
- [Hard start](https://runofsho.com/glossary/#hard-start): A segment that must begin at an exact clock time regardless of what came before, such as a live cross or a stream going on air.
- [Pad](https://runofsho.com/glossary/#pad): Flexible content or time that can be stretched or cut to make a show hit its end time. A host chat or a Q&A is often the pad.